Investments in Drinking Water and Wastewater Infrastructure to Protect Public Health and the Environment

  • Transportation and Infrastructure
  • Environment and Climate Change

May 25, 2021

Today, the Honourable Elvis Loveless, Minister of Transportation and Infrastructure and  Scott Simms, Member of Parliament for Coast of Bays-Central-Notre Dame, on behalf of the Honourable Catherine McKenna, Minister of Infrastructure and Communities, announced more joint funding for drinking water and wastewater projects in 21 communities in Central Newfoundland.

Grand Falls-Windsor will see the construction of a new ultraviolet disinfection building. This new infrastructure will benefit the community by increasing its capacity to treat and manage wastewater while meeting the provincial effluent quality requirements. Residents of 10 other municipalities will also benefit from upgrades to their wastewater infrastructure including new and improved lift stations, and water and sewer main replacements.

In addition, 12 municipalities will see improvements to their drinking water systems which include the rehabilitation and expansion of water supply mains and connections, new hydrants for improved fire safety, a new pump house building in the Town of Jackson’s Cove-Langdon’s Cove-Silverdale, and a new chlorination system in the Town of La Scie.

Together, these improvements will ensure residents continue to benefit from safe and reliable water and wastewater services for years to come. More information can be found in the backgrounder below.

The Government of Canada is investing more than $5.5 million, and the Government of Newfoundland and Labrador is providing over $6.2 million in these projects through the Green Infrastructure Stream (GIS) of the Investing in Canada plan. The municipalities and communities are contributing more than $3.4 million towards their respective projects.

Quotes
“We are always happy to work with town councils and our partners in Ottawa. This funding helps ensure that communities in our province have safe and reliable water and wastewater infrastructure.”
Honourable Elvis Loveless
Minister of Transportation and Infrastructure

“Significant milestones have been reached in recent years in efforts to increase access to safe and reliable water and wastewater systems. Over three years, our government has approved approximately 300 water projects through $100 million in provincial funding. The funding announced today for these communities throughout Central Newfoundland supports their efforts to improve their infrastructure and respond to their unique needs and challenges.”
Honourable Bernard Davis
Minister of Environment and Climate Change

“Investments in essential public infrastructure are vital to building healthy and resilient communities. The upgrades to the water and wastewater systems in these 23 communities will ensure residents benefit from safe and reliable essential services for years to come, while also protecting the environment. Canada’s infrastructure plan invests in thousands of projects, creates jobs across the country, and builds cleaner, more inclusive communities.”
Scott Simms, Member of Parliament for Coast of Bays—Central—Notre Dame, on behalf of the Honourable Catherine McKenna, Minister of Infrastructure and Communities

-30-

Learn more 

Investing in Canada Plan Project Map

Federal infrastructure investments in Newfoundland and Labrador

Investing in Canada: Canada’s Long-Term Infrastructure Plan

Follow us on Twitter @GovNL and @TW_GovNL

Like us on Facebook

Media contacts
Emily-Jane Gillingham
Transportation and Infrastructure
709-729-1758, 730-4607
emilygillingham@gov.nl.ca

Chantalle Aubertin
Office of the Minister of Infrastructure and Communities
613-941-0660
chantalle.aubertin@canada.ca

Media Relations
Infrastructure Canada
613-960-9251
Toll free: 1-877-250-7154
Email: infc.media.infc@canada.ca

Follow us on Twitter, Facebook and Instagram
Web: Infrastructure Canada

BACKGROUNDER

Project Information

Location Project Name Project Details Federal Funding Provincial Funding Municipal

Funding

Badger Rehabilitation of Three Lift Stations The replacement of three lift stations on Maple Street, Kinsmen Drive and the Trans-Canada Highway.

The Project will benefit the community by increasing its capacity to treat and manage wastewater.

$288,948 $361,185 $146,451
Beachside Main Street  Water and Sewer Upgrades The installation of approximately 300 meters of water and sewer main along Main Street will benefit 12 residences. $162,208 $202,760 $82,214*
Bishop’s Falls Greenridge Road Waterline Loop The supply and construction of 225 meters of local water pipes to connect the waterlines on Greenridge Road and First Avenue to create a looped network.

The project will benefit the community by increasing access to potable water.

$44,838 $44,838 $33,935
Botwood Water Main Replacement & Associated Upgrades – Sacrey’s Road The rehabilitation of 930 meters of water main and upgrades to 930 meters of road upon completion of the water main installation. Replacing the existing undersized water main will benefit the community by increasing access to potable water and by improving the quality of road infrastructure on Sacrey’s Road. $443,541 $443,541 $335,690
Burlington Water Main Extension The expansion of the current water system includes extending the watermain by 670 meters to include services to four more residences. In addition, four new fire hydrants will be installed to ensure fire safety as well as the ability to flush the watermain when necessary. $168,497 $210,621 $85,401
Cottlesville Retrofitting Two Sewage Lift Stations The rehabilitation of two sewage lift stations including the replacement of all mechanical and electrical 10components will result in a more reliable and efficient pumping station that will better serve the community. $90,683 $113,354 $45,962
Crow Head Mutford’s Cove Road – Water and Sewer – Phase 2 The installation of approximately 700 meters of sanitary sewer and 200 meters of forcemain. New sewer services for 16 residences, and placement new asphalt in the Town of Crow Head. $438,895 $548,619 $222,450
Embree Water Street Lift Station Upgrade The replacement of the internal mechanical and electrical equipment in the lift station will make it more efficient, improving the community’s ability to treat and manage wastewater. $63,658 $79,573 $32,265
Glenwood Water and Sewer Upgrades – Shea Ave. – Glenwood The rehabilitation of approximately 180 meters of sanitary sewer and water main as well as new water and sewer services for eight additional residences will provide better access to potable water and increase the community’s capacity to manage wastewater. $105,585 $131,981 $53,515
Grand Falls -Windsor Construction of an Ultra Violet Disinfection Building The construction of a new Ultraviolet (UV) disinfection building. The new UV disinfection system will help address both future increase in wastewater flows requiring treatment as well as improve the effluent quality to meet provincial requirements.

The project will benefit the community by increasing its capacity to treat and manage wastewater.

$922,686 $692,015 $928,999
Harbour Breton Upgrading Storm & Sewer Infrastructure – Godwin’s Hill/Canada Drive, Harbour Breton The replacing of 910 meters of sanitary and storm drainage pipes will increase capacity to manage wastewater by eliminating drainage problems.

The installation of a fire hydrant will provide residents with better fire protection.

$482,709 $603,386 $244,657
Jackson’s Cove – Langdon’s Cove – Silverdale Pump house and Water Intake Upgrades The construction of a new pump house building, wet well, 20 meters of water intake pipes, installation of new pumps, and a new hypochlorination system and associated works in the Town of Jackson’s Cove-Langdon’s Cove-Silverdale.

The Project will benefit the community by increasing access to potable water.

$100,215

 

 

$125,268

 

 

$50,793

 

 

La Scie New Chlorination System The construction of a chlorination building and the purchase and installation of a chlorination system will provide access to potable water for the community. $191,886 $239,858 $97,256
Lewisporte Pond Road Water, Sewer and Road Upgrade The replacement of approximately 200 meters of storm lines, approximately 200 meters of sanitary sewer lines, and upgrading approximately 400 meters of water lines on Pond Road. The scope will also include reinstating the asphalt and the curb associated with the project.

The project will benefit the community by improving access to potable water and by improving the community’s capacity to treat and manage wastewater and stormwater.

$223,420 $223,420 $169,093
Port Anson Rowsell’s Point Road and Port Anson Road The construction of 680 meters of new water mains including services, hydrants, and road reinstatement on a portion of Port Anson Road and on Rowsell’s Point Road.

Once complete, residents will have improved access to drinking water and sufficient main pressure for fire safety.

$291,294 $364,117 $147,640
Smith’s Harbour Water Supply System Upgrade The supply and construction of a water pumping system at Round Pond will allow water to be pumped into the municipal reservoir.

The project will supply the community of Smith’s Harbour with better and more reliable access to potable water.

$116,383 $145,479 $58,988
Springdale Booth Avenue Rehabilitation The replacement of sanitary sewer, storm sewer, and water line infrastructure to provide clean, safe drinking water to the community of Springdale. $173,889 $217,362 $88,134
St. Alban’s Wet Well Pump House Improvements Upgrades to the pump control system to reduce water overflow. In addition, a more efficient pump sequencing pattern of the three pumps will decrease energy usage and an aging deep well pump will be replaced. $145,113 $181,392 $73,549
Summerford Strong’s Island Water and Sewer Phase 1 The installation of 1600 meters of water and sewer lines will provide better access to potable water and increase the community of Strong Island’s capacity to manage wastewater. $742,744 $928,430 $376,454
Summerford Water and Sewer Improvements – Valves and Hydrants The replacement of valves and hydrants will ensure the continued functionality of the community’s water distribution system. $21,740 $27,175 $11,019
Triton Water and Sewer Upgrades – Lift Station Retrofits and New Booster Pump Upgrades to the existing lift stations, the installation of a new water booster pump and pump house will increase the town’s capacity to treat and manage wastewater and stormwater and increase access to potable water. $212,832 $266,040 $107,872
Twillingate Sewage Lift Station Retrofits Two sewage lift stations will be fully retrofitted, eliminating the risk of sewer backups impacting nearby properties and preventing overflows from entering the ocean. $90,683 $113,354 $45,962
2021 05 25 12:00 pm