- The Mineral Lands Division maintains a listing of service providers that offer fees for service assistance with various quarry-related needs such as applications, mapping, legal surveys, aggregate resource assessments, development, rehabilitation and closure plans, environmental assessment registration documents, stake-holder engagement, etc.
- Service Provider Listing.pdf
Quarry Rehabilitation & Closure
- Quarry permits and leases must be rehabilitated in accordance with the terms and conditions of the permit/lease in accordance with the Quarry Materials Act.
- Rehabilitation has multiple goals including:
- Restore the quarry site to a physically and chemically stable, and safe condition to protect public health and safety.
- To decommission the quarry site to a land use similar to its original use or another to a use that is compatible with neighboring land uses.
- Rehabilitation can take multiple forms, for example:
- Progressive rehabilitation requires you to rehabilitate the areas of your site that are no longer needed while you are extracting quarry resources in other areas of your site, or while you retain the permit, but you aren’t actively operating the site.
- Final rehabilitation must be completed for any site that will no longer be used (i.e., its quarry resources have been exhausted or are limited) or is no longer required by the permittee and cancelled.
- The standard terms and conditions of all quarry permits and leases outline comprehensive rehabilitation requirements (Schedule B, Section E), all of which are required for final rehabilitation.
- Common forms of rehabilitation include:
- Grading and Fill of Excavated Areas
- Rock faces sloped to a 2:1 gradient
- Unconsolidated aggregate (sand / gravel) faces sloped to 3:1 gradient
- Settling ponds and water sumps backfilled
- All material used for sloping or fill must be sourced from the quarry operation itself or from existing stockpiles of aggregate or overburden. Topsoil and grubbing material must be stockpiled separately to be used for revegetation.
- Importing of topsoil, overburden or other fill material is allowed but must be pre-approved by the Department.
- Revegetation and Regeneration of Quarry Site
- Topsoil and grubbing material excavated from the quarry operation must be stockpiled separately from overburden and aggregate product and remain on site for final rehabilitation and closure.
- Topsoil and grubbing material are to be spread over entire site and select slopes as directed.
- Hydroseeding or planting may be required when there is not enough topsoil or grubbing to cover the site or to mitigate impacts on visibility or viewscape.
- Surface Water and Drainage
- There shall be no areas of accumulated or ponded water in the quarry (e.g., settling ponds, ponded water in low-lying areas).
- Prior to abandoning the site, drainage measures must be implemented to prevent future accumulation of water once the site is closed.
- You must notify the Department of any draining ditches, culverts, check damns remaining after closure of the site.
- Install sediment control devices to prevent sediment infiltration of natural water bodies.
- Equipment and Buildings
- All equipment such as concrete batch plants, asphalt plants, and weigh scales must be temporary in construction. No permanent equipment can be installed unless approved by the Department.
- Outbuildings used for office space or storage must be temporary in construction. No permanent outbuildings are permitted to be constructed unless approved by the Department.
- All equipment, buildings and structures must be removed from site prior to submitting a request to close the quarry.
- Clean and Orderly Site
- Remove all scrap equipment and garbage from the site.
- Remove all imported material including waste asphalt or concrete from the site.
- Remove all equipment from the site including heavy equipment, screeners, culverts, scrap steel, etc.
- Entrances and Exits must be decommissioned
- Grading and Fill of Excavated Areas
- If you have any questions or concerns regarding the rehabilitation requirements for a specific quarry site, please contact the Department by email at QuarryInspections@gov.nl.ca
Working in a Transportation and Infrastructure Quarry
- The Department of Transportation and Infrastructure maintains quarries across the province for use by government or companies awarded government contracts.
- Currently active quarry permits:
File Number General Location Size (Ha) Expiry Date 7117175 1.3km east Flat Bay Brook Bridge off T.C.H. 5 7/29/2026 7119234 Approx 500m south of Green Island Cove 2 5/31/2026 7118483 2km north of Eddies Cove West off R430 1 5/30/2026 7116053 Glenburnie, 100m from Middle Brook 1 5/31/2026 7117914 Approx 7km South of Cooks Harbour 1 5/31/2026 7113564 North Side of Route 333, 2 km east of Stag Harbour 5 6/27/2026 7115314 2 km south of Deep Bay Intersection with Route 333 2 6/27/2026 7115315 Fogo Island, 0.4 km from junction of Route 333 5 6/27/2026 7119291 South of Green Island Cove 2 6/19/2026 7115079 1/10TH km from Flat Bay Access Road & T.C.H. Inter 8.75 8/31/2026 7116062 7km South of Inter Route 362&362-10, Pools Cove 5 7/10/2026 7119179 2.1km West R360 on William's Rd (Resource Road) 4 7/10/2026 7119005 83km from TCH, East of R360, Berry Hill Pond 4 7/10/2026 7116063 9km South of Intersection Route 362-362-10, Pools Cove 5 7/10/2026 7115163 0.2 km from Furby's Cove Intersection 5 7/10/2026 7115537 South of Wreck Cove Intersection with Route 363 0.5 7/10/2026 7118317 Route 220 (Jims Pond); 150 m generally East at 0.61 km Northeast of pond 1.01 4/15/2026 7115604 3.8 km north of Pieduck Cove Inter on Route 220 2 4/15/2026 7114363 Easterly from Route 210, 500m east of Famine Brook 4 4/15/2026 7114364 White Point Road, Frenchmans Cove 2 4/15/2026 7119007 Route 432; 600 m West of Route 433 junction 2 9/22/2026 7118191 3.1 km South of Daniel's Harbour Motel 2 8/19/2026 7115379 1 km east of Hampden Turnoff on T.C.H. 5 7/29/2026 71110946 4.7 km south of intersection Route 435 with Route 430, located on Route 430 0.94 11/25/2026 7118318 Routte 220; South side at 4.0 km W of Lamaline 0.874 1/29/2027 7116396 Approx 1.2km East Point May Inter on Route 220 0.42 1/29/2027 7119235 10.5km North of Roddickton 1.5 8/31/2026 7115967 Squid Cove Forest Access Road 5 8/31/2026 7118878 7118878 4 12/17/2026 7114321 TCH (Peak Pond); South side at 0.25 km West of Spread Eagle River 5 11/13/2026 7116682 Approx 1km West of Greenspond Causeway Bridge 2.74 11/23/2026 7118869 Route 10 (South side) at Tors Cove Depot 6.8 2/4/2027 7115124 400m from Route 231 at Robinsons Bight, Long Pond 4.12 1/18/2027 7115484 Route 10, 0.2 km North of Three Gully River 5 6/6/2026 7115505 Between Point LaHaye and St.Mary's 1.71 6/6/2026 7115916 1.7km north of Inter with Route 93 & Route 93-10 5 6/6/2026 7115485 Approx 6km northeast of St.Shotts on Route 10-52 5 6/6/2026 - Companies that have been awarded a contract for provincial infrastructure-related projects (e.g., highway construction, winter sand, etc.) can apply to operate in a TI quarry site under a Subordinate Quarry Permit.
- All requests to operate in a TI quarry must be submitted to TIQuarries@gov.nl.ca
Heavy Civil Association
-
- The Heavy Civil Association of Newfoundland and Labrador Inc. is an important stakeholder in the quarry industry. The Department actively engages with the Association to ensure that major changes to the regulation of quarry resources are communicated to their membership.
-