Proponent: World Energy GH2 Limited Partnership
Summary of Environmental Assessment Process
Project Description:
The proponent is proposing to construct and operate a maximum 1 gigawatt (GW), 164-turbine onshore wind farm on the Port au Port Peninsula with the associated transmission and supporting infrastructure to power a 0.5 GW hydrogen/ammonia production facility in the port of Stephenville.
- June 21, 2022 – The undertaking was registered.
- July 27, 2022 – Deadline for public comments.
- August 5, 2022 – The Minister’s decision is due.
- August 5, 2022 – An Environmental Impact Statement (EIS) is required.
- August 5, 2022 – Environmental Assessment Committee (EAC) appointed.
- December 2, 2022 – The Minister is due to deliver EIS Guidelines to the proponent.
- September 29, 2022 – Draft EIS Guidelines for public review.
- November 8, 2022 – Deadline for public comments on Draft EIS Guidelines.
- December 13, 2022 – Final EIS Guidelines Approved.
- August 22, 2023 – EIS Submitted – Public Comments Invited.
- October 11, 2023 – Deadline for public comments on the EIS.
- October 31, 2023 – The Minister’s decision on the acceptability of the EIS is due.
- October 31, 2023 – The Minister determined that the EIS Requires Additional Work.
- January 30, 2024 – Amendment to the EIS submitted – public comments invited.
- March 20, 2024 – Deadline for public comments on the Amendment to the EIS.
- April 9, 2024 – The Minister’s decision on the acceptability of the Amendment and EIS is due.
- April 9, 2024 – The Minister determined that the EIS and Amendment are acceptable.
- April 9, 2024 – The Minister announced that the project is released with conditions.
- Documents:
- Registration (6.2 MB)
- Appendix 1 (5.9 MB)
- Appendix 2 (9.7 MB)
- Decision Letter (691 KB)
- Draft EIS Guidelines (1 MB)
- Decision Letter EIS Guidelines (486 KB)
- Final EIS Guidelines (798 KB)
- Environmental Impact Statement:
- Main Document:
- Executive Summary (19 MB)
- Table of Concordance (533 KB)
- Table of Contents and Abbreviations (366 KB)
- Chapters 1-3 (12 MB)
- Chapters 4-7 (7 MB)
- Chapters 8-12 (10 MB)
- Chapters 13-20 (12 MB)
- Chapters 21-26 (7MB)
- Appendices:
- Appendix 1A-D (2 MB)
- Appendix 2A-C (5 MB)
- Appendix 2D-I (3 MB)
- Appendix 4A-D (10 MB)
- Appendix 6A-C (2 MB)
- Appendix 7 (263 KB)
- Appendix 8 (4 MB)
- Appendix 11 (1 MB)
- Appendix 19A (27 MB)
- Appendix 19B-F (14 MB)
- Appendix 23 (215 KB)
- Appendix 24 (6 MB)
- Appendix 26 (391 KB)
- Baseline Studies:
- Atmospheric Environment (2 MB)
- Aquatic Environment (28 MB)
- Terrestrial Environment (26 MB)
- Socio-Economic Environment and Land and Resource Use (19 MB)
- Main Document:
- Decision Letter – Environmental Impact Statement (452 KB)
- Amendment to the Environmental Impact Statement
- Main Document (9 MB)
- Appendices:
- Chapter 2:
- Appendix 2-A Fish and Fish Habitat (64 MB)
- Appendix 2-B Bird and Bat Baseline Study (4 MB)
- Appendix 2-C Land Cover Classification and Rare Plants (24 MB)
- Appendix 2-D 2023 Muskrat Technical Data Report (7 MB)
- Appendix 2-E, 2-F, 2-G, 2-H, 2-I, 2- J and 2-K (12 MB)
- Project Nujio’qonik: Baseline Ambient Air Quality Monitoring Study
- Species at Risk Impacts Mitigation and Monitoring Plan TOC
- Groundwater Monitoring Plan TOC
- Surface Water Monitoring Plan TOC
- Avifauna Impacts Mitigation and Monitoring Plan TOC
- Outfitters Effects Monitoring Plan TOC
- Updated Transportation Impact Study and Traffic Management Plan
- Chapter 4:
- Appendix PPD7-A, PPD9-A and PPD-11-A (14 MB)
- Construction Debris Storage
- Preliminary Wastewater Effluent Composition
- Detailed Emission Inventory
- Appendix WRM4-A – Technical Memo on Expansion of Town of Stephenville Potable Water Supply (10 MB)
- AppendixWRM13-A – Industrial Water Demand and Supply Assessment (76 MB)
- Appendix WRM18-A, WRM20-A and WRM33-A (11 MB)
- Noel’s Pond Water Levels
- Flood Emergency Response Plan
- Public Water Supply Areas Intersected by the Proposed 230 kV Transmission Line
- Appendix WRM36-A and WRM42-A (18 MB)
- EIS Input on Groundwater Impacts
- Water Usage for Industrial and Residential Users Gull (Mine) Pond
- Appendix WRM53-A and WRM71-A (16 MB)
- Codroy Flooding Risk Assessment
- Sludge Characterization
- Appendix PPD7-A, PPD9-A and PPD-11-A (14 MB)
- Chapter 5 – Appendix FFA41-A and FFA43-A s (6 MB)
- Weather Radar Advice
- Community Based Coastal Resource Inventory Maps
- Chapter 6 – Appendix HCS1-A, HSC2-A, HCS1-C and HCS20-A (14 MB)
- Mapbook – Receptor Locations Near the Project Area Considered in the EIS
- Public Receptors Considered in the EIS and Distances to Nearest Turbine
- Closet Non-Public Receptors (e.g. Residences/Cabins) to each Turbine as considered in the EIS
- Updated Commitments Table from the EIS
- Chapter 7
- Appendix EB30-A and MMD3-A (12 MB)
- System Impact Study Process Overview
- Mapbook: Quarries, Mining Leases and Exempt Mineral Lands in the Project Area
- Appendix MMD3-B and MMD3-C (16 MB)
- Mapbook: Producing Mines, Mineral Claims, and Mineral Commodity Occurrences in the Project Area
- Prospective Quarry Locations
- Appendix MMD6-A and MMD16-A (14 MB)
- Mapbook; Petroleum Industry Activity in the Project Area
- Prospective Quarry Locations
- WebMap of Mineral Claims (Revised EIS Figure 4.12)
- Appendix EB30-A and MMD3-A (12 MB)
- Chapter 9 – Appendix DMPA1-A and DMPA10-A (7 MB)
- Mapbook – Land Use
- Noise and Vibration Monitoring Locations
- Chapter 14 – Appendix ECCC57-A Mapbook – Proposed Surface Water Monitoring Sampling Locations (3 MB)
- Chapter 2:
- Acceptability of EIS and Amendment (486 KB)
- Decision Letter (678 KB)
- Attachment 1 – Conditions of Release (839 KB)
- Registration (6.2 MB)
- Public Notices:
- Project Registered (142 KB)
- EIS Required and EAC Appointed (135 KB)
- Draft EIS Guidelines for Public Review (121 KB)
- Final EIS Guidelines Issued (85 KB)
- EIS Submitted for Review – Public Comments Invited (113 KB)
- EIS Decision (90KB)
- Amendment to the EIS Submitted (139 KB)
- EIS Accepted (86 KB)
- Project Released (86 KB)