Proponent: Sunshine Investments Inc.
Summary of Environmental Assessment Process
Project Description:
The proponent is proposing a regional, year–round, abattoir to service the central region of the province. The undertaking is located in the community of Northern Arm and the site is bound to the south by Northern Brook Resource Road and to the west by Rowsell’s Lake Road.
- September 22, 2020 – The undertaking was registered.
- October 30, 2020 – Deadline for public comments.
- November 6, 2020 – The Minister’s decision is due.
- December 3, 2020 – Environmental Preview Report (EPR) is required.
- December 3, 2020 – Environmental Assessment Committee is appointed.
- February 1, 2021 – EPR Guidelines are due to be issued.
- January 27, 2021 – The Minister issued the EPR Guidelines.
- April 1, 2021 – EPR Submitted for review.
- May 27, 2021 – Minister’s EPR decision.
- September 17, 2021 – Revised EPR submitted for review.
- October 22, 2021 – Deadline for public comments on revised EPR.
- November 1, 2021 – The Minister’s decision is due.
- October 29, 2021 – The Minister announced the project is released.
- Documents:
- Registration (10 MB)
- Decision Letter (58 KB)
- EPR Guidelines (47 KB)
- Environmental Preview Report (21 MB)
- EPR Part 2 (33 MB)
- EPR Part 3 (6 MB)
- EPR Decision Letter (495 KB)
- Revised EPR (1.83 MB)
- Revised EPR Decision Letter (465 KB)
- Public Notices:
- Project Registered (440 KB)
- EPR Required and Committee Appointed (50 KB)
- EPR Guidelines Issued (44 KB)
- EPR Submitted (134 KB)
- EPR Deficient (355 KB)
- Revised EPR Submitted (107 KB)
- Project Released (439 KB)
Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free