Registration Number: 2192

Grand Falls-Windsor – Glenwood Transmission Line Decommissioning

Proponent: Newfoundland Power Inc.

Summary of Environmental Assessment Process

Project Description:

The proponent is proposing to decommission a 70-kilometre section of the 101L and 102L transmission lines between the Towns of Grand Falls-Windsor and Glenwood. These two sections of the transmission line are no longer required as the grid system has been reconfigured. Project activities include the dismantling, removal, and disposal of sections of each line between 32 kilometres to 38 kilometres in length.

  • March 24, 2022 – The undertaking was registered.
  • April 29, 2022 – Deadline for public comments.
  • May 8, 2022 – The Minister’s decision is due.
  • June 22, 2022 – The Minister’s decision is due (extended).
  • July 13, 2022 – The Minister’s decision is due (extended).
  • July 8, 2022 – The Minister determined the project is released.