Registration Number: 1431

JAG Cranberry Farm

Proponent: JAG Sod Farm Ltd.

Summary of Environmental Assessment Process

Project Description:

The proposal is to develop a 60 hectare domed peat bog located 12 kilometres south of the TCH on the west side of the Bay D’espoir Highway. Construction will include the development of a portion of the bog into approximately 6 hectares of cranberry field beds. This development will include an irrigation/ sediment pond, auxiliary buildings, water control structures, drainage tile in the bed, and berm construction. Harvesting includes flooding each field with 45 centimetres of water, independently, and removal with a cranberry beater. The project is scheduled to commence in July, 2009 if approved.

  • June 8, 2009 – The undertaking was registered.
  • July 15, 2009 – Public comments are due.
  • July 23, 2009 – The Minister’s decision is due.
  • July 31, 2009 – The Minister Released the undertaking.