Proponent: North Atlantic Refining Limited
Summary of Environmental Assessment Process
Project Description:
The proponent intends to upgrade of its refinery facility in Come By Chance, through a process known as a debottle necking, to remove process constraints and permit improved production and efficiency. The project will improve the economics and sustainability of the refinery and result in a reduction in greenhouse gas and criteria air contaminant emissions. Many existing pumps, heat exchangers, compressors and process vessels will be modified or replaced. A new crude blending tank will also be constructed. The project is to be carried out in phases beginning in the fall of 2010 and ending in the winter of 2011.
- August 25, 2010 – The undertaking was registered.
- September 30, 2010 – Public comments are due.
- October 8, 2010 – The Minister’s decision is due.
- October 28, 2010 – The undertaking was released.
- Documents:
- Registration (3.2 MB)
- Public Notices:
- Project Registered (29 KB)
- Project Released (39 KB)