Registration Number: 1547

Canning’s Cove Big Pond ATV Trail

Proponent: Mr. Levi Penney

Summary of Environmental Assessment Process

Project Description:

The proponent plans to extend an existing trail by approximately 3 kilometres to allow access to several remote cabins. The trail will be located in the Big Pond area, near Canning’s Cove, Bonavista Bay. A minimum 50 metre buffer will be maintained between the trail and Big Pond. Construction is expected to take one week.

  • December 7, 2010 – The undertaking was registered.
  • January 13, 2011 – Public comments are due.
  • January 21, 2011 – The Minister’s decision is due.
  • March 3, 2011 – The undertaking was released.

Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free