Registration Number: 1762

Peter’s Arm Aggregate Quarry

Proponent:  D. Byrne and Sons Ltd.

Summary of Environmental Assessment Process

Project Description:

The proponent has submitted a proposal to develop a 10-hectare sand and gravel pit located 500 metres from Route 350, south of Peter’s Arm in the Town of Botwood.  The operation will include crushing and screening and will supply aggregate to Botwood and the surrounding area.  The green-field site is accessible from Route 350 via an existing resource road and will operate from May to November in 2015.

  • September 9, 2014 – The undertaking was registered.
  • October 15, 2014 – Deadline for public comments.
  • October 23, 2014 – The Minister’s decision is due.
  • November 26, 2014 – The Minister announced that the project is released.