Proponent: NARL Fuels LP
Summary of Environmental Assessment Process
Project Description:
The proponent proposes the construction and operation of a delayed coker complex equipped with a small integrated crude oil fractionation unit, a distillate hydrotreater, and assorted utilities in Come by Chance, northwest of the existing refinery. The petroleum facility will consist of a 26,000 barrel per day delayed coker, equipped with a 40,000 barrel per day fractionation unit and a 17,000 barrel per day distillate hydrotreater.
- July 11, 2019 – The undertaking was registered.
- August 16, 2019 – Deadline for public comments.
- August 25, 2019 – The Minister’s decision is due
- October 10, 2019 – Environmental Preview Reports required
- October 25, 2019 – Environmental Assessment Committee Appointed
- November 12, 2019 – The deadline for the issuance of EPR guidelines has been extended.
- April 14, 2022 – Project withdrawn from EA review.
- Documents:
- Registration (910 KB)
- Minister’s EPR Letter
- Public Notices:
- Project Registered (333 KB)
- Environmental Preview Reports Required (486 KB)
- Environmental Assessment Committee Appointed (354 KB)
- Project Withdrawn (25 KB)
Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free