Project Description:

The proponent proposes the construction and operation of a delayed coker complex equipped with a small integrated crude oil fractionation unit, a distillate hydrotreater, and assorted utilities in Come by Chance, northwest of the existing refinery. The petroleum facility will consist of a 26,000 barrel per day delayed coker, equipped with a 40,000 barrel per day fractionation unit and a 17,000 barrel per day distillate hydrotreater.

  • July 11, 2019 – The undertaking was registered.
  • August 16, 2019 – Deadline for public comments.
  • August 25, 2019 – The Minister’s decision is due
  • October 10, 2019 – Environmental Preview Reports required
  • October 25, 2019 – Environmental Assessment Committee Appointed
  • November 12, 2019 – The deadline for the issuance of EPR guidelines has been extended.
  • April 14, 2022 – Project withdrawn from EA review.