Proponent: Newfoundland Power In.
Summary of Environmental Assessment Process
Project Description:
The proponent is proposing to rebuild a 58-kilometre section of the 124L power transmission line from Gambo to Port Blandford. This proposed work will include the construction of a new corridor adjacent to the existing easement and a new power transmission line. The Project will be built in two phases, with Phase 1 being completed in 2021 and Phase 2 in 2022.
- November 2, 2020 – The undertaking was registered.
- December 10, 2020 – Deadline for public comments.
- December 17, 2020 – The Minister’s decision is due.
- December 21, 2020 – The Minister announced the project is released.
- Documents:
- Registration (4.52 MB)
- Decision Letter (1.48 MB)
- Public Notices:
- Project Registered (44 KB)
- Project Released (49 KB)