Registration Number: 2113

Parson’s Pond Four Ponds ATV Trail

Proponent: Roberts’ Outfitting Ltd.

Summary of Environmental Assessment Process

Project Description:

The proponent is proposing to construct a 1 kilometre ATV trail, approximately 25 kilometres south east of Parson’s Pond in the Main River Waterway Provincial Park. The ATV trail would be constructed between the Nalcor Transmission Line and Four Ponds Outfitting Camp. The proponent is proposing to construct the trail to be able to access Four Ponds Outfitting Camp.

  • December 16, 2020 – The undertaking was registered.
  • January 21, 2021 – Deadline for public comments.
  • January 30, 2021 – The Minister’s decision is due.
  • January 14, 2021 – Project withdrawn.

Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free