Project Description:

The proponent is proposing to remove and replace existing wharf infrastructure with a finger pier wharf, construct a new storage building, and construct a protective breakwater in the Raleigh Small Craft Harbour. This project is designed to demolish the deteriorated wharf facilities and construct a new facility that will better meet the needs of the current users.

  • November 30, 2021 – The undertaking was registered.
  • January 7, 2022 – Deadline for public comments.
  • January 14, 2021 – The Minister’s decision is due.
  • February 9, 2022 – The Minister announced the project is released.