Registration Number: 911

Hawke Hills Wind Power Project (Four Mile Pond) – CHI Hydroelectric Company Inc.

Proponent: CHI Hydroelectric Company Inc.

Summary of Environmental Assessment Process

Project Description: The proponent plans to construct and operate a 15 MW wind power project at Four Mile Pond, Hawke Hills approximately 6 kilometres south of the Town of Holyrood, as per Newfoundland and Labrador Hydro’s request for proposals. The proposed project is for 25 individual wind turbine generators. The wind turbines are horizontal axis, three bladed wind energy converters with a maximum hub height of 60 metres and rotor diameter of between 40 and 50 metres.

  • December 6, 2000 – The undertaking was registered.
  • March 16, 2001 – The Minister announced that the proponent had withdrawn the project.

Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free