Registration Number: 2234

Shoal Cove to Chimney Cove Multi Use Trail

Proponent: Natalia Crocker

Summary of Environmental Assessment Process

Project Description:

The proponent is proposing to construct an approximately 6160-metre multi-use trail from Shoal Cove to Chimney Cove. The trail construction will include clearing and grubbing and crossings of small waterways. Work is scheduled to begin during the summer of 2023.

  • February 2, 2023 – The undertaking was registered.
  • March 10, 2023 – Deadline for public comments.
  • March 19, 2023 – The Minister’s decision is due.
  • March 17, 2023 – The Minister determined the project is released.