Project Description:

The proponent is proposing to expand the Indian Head Hatchery in Stephenville. The expansion will provide smolts to the licensed sea cages that belong to Northern Harvest Sea Farms. The project is intended to improve production capacity and quality of salmon smolts produced for the company and to increase salmon aquaculture production for the province. The project includes: upgrades to improve efficiency of the existing facility; expansion of the hatchery; and new supporting infrastructure such as freshwater and saltwater supply and effluent treatment and discharge.

  • July 17, 2018 – The undertaking was registered.
  • August 21, 2018 – Deadline for public comments.
  • August 31, 2018 – The Minister’s Decision is due.
  • September 6, 2018 – The Minister announced that the project is released with conditions.
  • September 20, 2018 – Appeal of Minister’s Decision.
  • October 25, 2018 – Decision on Appeal.
  • November 9, 2018 – Appeal of Minister’s Decision.
  • December 5, 2018 – Decision on Appeal.
  • July 15, 2021 – Minister determined that an Environmental Preview Report (EPR) is required.
  • August 12, 2021 – Environmental Assessment Committee appointed.
  • September 12, 2021 – EPR Guidelines due to be issued.
  • September 26, 2021 – EPR Guidelines due to be issued (extended).
  • October 10, 2021 – EPR Guidelines due to be issued (extended).
  • October 28, 2021 – EPR Guidelines due to be issued (extended).
  • December 8, 2021 – EPR Guidelines due to be issued (extended).
  • December 16, 2021 – EPR Guidelines issued.
  • August 9, 2023 – EPR Submitted for Review.
  • September 13, 2023 – Deadline for public comments on the EPR.
  • September 23, 2023 – The Minister’s decision on the EPR is due.
  • October 7, 2023 – The Minister’s decision on the EPR is due (extended).
  • October 21, 2023 – The Minister’s decision on the EPR is due (extended).
  • October 25, 2023 – The Minister determined that an Environmental Impact Statement (EIS) is required.
  • February 22, 2024 – The Minister is due to deliver the EIS Guidelines to the proponent.
  • January 12, 2024 – Draft EIS Guidelines for public review.
  • February 21, 2024 – Deadline for public comments on Draft EIS Guidelines.
  • March 7, 2024 – The Minister is due to deliver the EIS Guidelines to the proponent (extended).
  • March 7, 2024 – Final EIS Guidelines Approved.