Proponent: Marathon Gold Corporation
Summary of Environmental Assessment Process
Project Description:
The proponent is proposing to develop a gold mine approximately 55 kilometres southwest of Millertown in the central region. The project includes four potential mining deposits: Leprechaun, Sprite, Marathon, and Victory deposits. Standard surface mining techniques will be used in open pit construction and operation. The project will involve waste rock disposal piles; crushing and stockpiling areas; heap leach processing; conventional milling; processing facilities; and tailings management areas. It will require personal accommodations and supporting infrastructure including roads; power lines; buildings; and water and effluent management facilities. The construction period is expected to last 18-24 months followed by an estimated mine operation life of 13 years. The project will operate 24 hours per day, seven days a week on a 12-hour shift basis.
- April 16, 2019 – The undertaking was registered.
- May 21, 2019 – Deadline for public comments.
- May 31, 2019 – The Minister’s decision is due.
- June 21, 2019 – The Minister announced that an Environmental Impact Statement (EIS) is required.
- July 3, 2019 – Environmental Assessment Committee appointed.
- October 17, 2019 – Draft EIS Guidelines for public review.
- February 10, 2020 – Final EIS Guidelines approved.
- November 3, 2020 – EIS Submitted – Public Comments Invited.
- December 23, 2020 – Deadline for public comments on the EIS.
- January 12, 2021 – The Minister’s decision on the acceptability of the EIS is due.
- February 2, 2021 – Extended deadline for the Minister’s decision on the acceptability of the EIS.
- February 10, 2021- The Minister announced that the EIS required additional work.
- August 6, 2021 – Amended EIS submitted – public comments invited.
- September 26, 2021 – Deadline for public comments on the Amended EIS.
- October 16, 2021 – The Minister’s decision on the acceptability of the Amended EIS is due.
- October 23, 2021 – The Minister’s decision is due (extended).
- October 29, 2021 – The Minister’s decision is due (extended).
- October 29, 2021 – The Minister announced the amended EIS requires more work.
- January 7, 2022 – Second amendment to the EIS submitted – public comments invited.
- March 3, 2022 – Deadline for public comments on the second amendment to the EIS.
- March 18, 2022- Minister’s decision on the acceptability of the EIS, including Amendments 1 and 2, is due.
- March 17, 2022 – The Minister announced that the EIS and Amendments are acceptable.
- March 17, 2022 – The Minister announced that the project is released with conditions.
- August 25, 2022 – The Minister approved the environmental protection plan (EPP) for mining construction activities.
- October 6, 2022 – The Minister approved Conditions of Release.
- Documents:
- Registration (14 MB)
- Decision Letter (40 KB)
- Draft EIS Guidelines (904 KB)
- Decision Letter EIS Guidelines (28 KB)
- Final EIS Guidelines (1.3 MB)
- Environmental Impact Statement:
- Main Document:
- Table of Contents / Executive Summary (2.4 MB)
- Summary of EIS (6 MB)
- Chapters 1-3 (13.5 MB)
- Chapters 4-6 (10.6 MB)
- Chapter 7 (21 MB)
- Chapters 8-12 (20.2 MB)
- Chapters 13-19 (12.9 MB)
- Chapters 20-23 (5.6 MB)
- Appendices:
- Chapter 1 (3.8 MB)
- Chapter 2 (87.6 MB)
- Chapter 3 (4.5 MB)
- Chapter 5 (19.1 MB)
- Chapter 6 (2.6 MB)
- Chapter 7 (18.6 MB)
- Chapter 10 (311 KB)
- Chapter 17 (19.6 MB)
- Chapter 21 (2.1 MB)
- Baseline Studies:
- Dam Safety (24.6 MB)
- Woodland Caribou (36.6 MB)
- Water Resources (37.5 MB)
- Fish, Fish Habitat & Fisheries (18.8 MB)
- Acid Rock Drainage / Metal Leaching (15.2 MB)
- Atmospheric Environment (10.8 MB)
- Avifauna, Other Wildlife and Their Habitats (27.2 MB)
- Species at Risk / Conservation Concern (10.4 MB)
- Communities and Economy (5.8 MB)
- Historic Resources (5.9 MB)
- Main Document:
- Ministers Decision on the Acceptability of EIS (189 KB)
- Amended Environmental Impact Statement
- Main Document
- Part 1 (704 KB)
- Part 2 (1 of 2) (6.22 MB)
- Part 2 (2 of 2) (4.21 MB)
- Appendix
- Appendix A (9.85 MB)
- Appendix B (157 KB)
- Appendix C (222 KB)
- Appendix D (4.51 MB)
- Appendix E (1.05 MB)
- Appendix F (878 KB)
- Appendix G (9.06 MB)
- Appendix H (19.1 MB)
- Appendix I (1.11 MB)
- Appendix J (17.2 MB)
- Main Document
- Ministers Decision on the Acceptability of Amended EIS (799 KB)
- Second Amendment to the Environmental Impact Statement
-
- Main Document (9.24 MB)
- Appendix A (4.29 MB)
- Appendix B (14.3 MB)
- Appendix C (20.7 MB)
- Appendix D (24.9 MB)
- Acceptability of EIS and Amendments 1 and 2 (107 KB)
- Decision Letter (3.16 MB)
-
- Condition of Release (August 25, 2022)
- EPP Approved – Mining Construction (235 KB)
- EPP – Mining Construction (6 MB)
- Conditions of Release (October 6, 2022)
- Analysis of Preconstruction Conditions (25 KB)
- Decision Letter (540 KB)
- Public Notices:
- Project Registered (42 KB)
- EIS Required (76 KB)
- Environmental Assessment Committee Appointed (53 KB)
- Draft EIS Guidelines for Public Review (42 KB)
- Final EIS Guidelines Approved (40 KB)
- EIS Submitted for Review – Public Comments Invited (43 KB)
- EIS Required Additional Work (72 KB)
- Amended EIS Submitted (135 KB)
- Amended EIS Requires Additional Work (439 KB)
- Seconded Amendment to the EIS Submitted (120 KB)
- EIS Accepted (357 KB)
- Project Released (357KB)
- EPP Approved (110 KB)
- Conditions of Release Approved (110 KB)